JOB-1082Paid

EV Charging Expansion Phase 2 — Ironwood Marina

Ironwood Marina · Building B — Front Office

$5,067
EV Charger Install

Scope of work

Add EV charging capacity including panel work and conduit run. Permit and inspection included. Work to be performed outside business hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
MaterialLevel 2 EV Charger, 48A Hardwired2 ea$862.22$1,724.44
Material20A Single-Pole Breaker10 ea$16.25$162.50
Material20A Double-Pole Breaker4 ea$36.97$147.88
LaborElectrical labour — ev charger install25.7 hr$117.96$3,031.69
Total$5,066.51

Customer

Open
Ironwood Marina
Bethany Ashford
Project Manager
8055 Cypress Bend Ct
Wesley Chapel, FL 34408
Assigned crew
Crew 3 — Residential

Timeline

  1. Lead created
    Dec 7, 2020
  2. Won
    Dec 22, 2020
  3. Scheduled
    Jan 11, 2021
  4. Completed
    Jan 14, 2021

Documents