EV Charging Expansion Phase 3 — Palm Terrace Fellowship Church

Palm Terrace Fellowship Church · Building B — Annex

$8,083
EV Charger Install

Scope of work

Add EV charging capacity including panel work and conduit run. Customer to provide site access during working hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material12 AWG THHN Copper, White — 500 ft spool1 spool$200.81$200.81
Material12/3 NM-B w/ Ground — 250 ft coil3 coil$253.23$759.69
Material400A Meter Main Combo, 42-space1 ea$1,721.36$1,721.36
LaborElectrical labour — ev charger install45.8 hr$117.94$5,401.52
Total$8,083.38

Customer

Open
Palm Terrace Fellowship Church
Danielle Everly
Facilities Director
2769 Kingfisher Ln
Plant City, FL 33613
Assigned crew
Crew 2 — Service

Timeline

  1. Lead created
    May 6, 2023
  2. Won
    May 21, 2023
  3. Scheduled
    Jun 15, 2023
  4. Completed
    Jun 16, 2023