Standby Generator Install — 22 kW, Marsh Landing Auto Center

Marsh Landing Auto Center · Warehouse

$18,831
Generator Install

Scope of work

Set generator pad, run gas and electrical, commission unit. Includes as-built markup on completion. Customer to provide site access during working hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
MaterialAutomatic Transfer Switch, 200A5 ea$1,553.66$7,768.30
Material4/0 AWG Aluminum SER Cable157 ft$8.22$1,290.54
PermitPermit and inspection fees1 ea$278.81$278.81
LaborElectrical labour — generator install80.5 hr$117.93$9,493.55
Total$18,831.20

Job photos

3 from the field · click to enlarge

Activity

Notes on this job

  • JA
    Junia AldermanJan 2

    Permit submitted. Waiting on the county.

  • JA
    Junia AldermanDec 27

    Materials staged at the shop, ready for Monday.

  • EV
    Emmett VanceDec 13

    Found existing wiring in worse shape than quoted. Flagged to customer.

Customer

Open
Marsh Landing Auto Center
Desmond Ellsworth
Operations Manager
7510 Sable Ridge Blvd
Plant City, FL 33727
Assigned crew
Crew 4 — Power & Standby

Timeline

  1. Lead created
    Dec 7, 2025
  2. Won
    Dec 26, 2025
  3. Scheduled
    Jan 1, 2026
  4. Completed
    Jan 4, 2026