EV Charging Expansion Phase 1 — Sandpiper Charter Academy

Sandpiper Charter Academy · Warehouse

$7,181
EV Charger Install

Scope of work

Add EV charging capacity including panel work and conduit run. All work per NEC and local amendments. Includes as-built markup on completion.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material4/0 AWG Aluminum SER Cable359 ft$8.22$2,950.98
Material6 AWG Bare Copper Ground2 ft$2.92$5.84
LaborElectrical labour — ev charger install35.8 hr$118$4,224.44
Total$7,181.26

Customer

Open
Sandpiper Charter Academy
Imani Whitaker
Facilities Director
708 Sawgrass Reach Dr
Lutz, FL 33719

Timeline

  1. Lead created
    Oct 1, 2023
  2. Bid lost
    Oct 22, 2023

Lost: Budget not approved this cycle

Documents