JOB-1215Paid

New Construction Rough-In — Unit 4, Heron Cove Self Storage

Heron Cove Self Storage · Building A — Main Building

$75,628
New Construction Rough-In

Scope of work

Complete electrical rough-in per approved drawings. Permit and inspection included. Final walkthrough with customer before sign-off.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
MaterialType 2 Whole-Home Surge Protective Device3 ea$260.71$782.13
Material4/0 AWG Aluminum SER Cable364 ft$8.22$2,992.08
PermitPermit and inspection fees1 ea$106.12$106.12
LaborElectrical labour — new construction rough-in608 hr$118.01$71,747.50
Total$75,627.83

Job photos

4 from the field · click to enlarge

Activity

Notes on this job

  • JA
    Junia AldermanJul 31

    Materials staged at the shop, ready for Monday.

  • EV
    Emmett VanceJul 26

    Permit submitted. Waiting on the county.

  • AssistantJul 14

    Matched supplier invoice to this job and updated material costs.

Customer

Open
Heron Cove Self Storage
Victor Jessup
Operations Manager
4373 Stonegate Cir
Temple Terrace, FL 33784
Assigned crew
Crew 1 — Commercial

Timeline

  1. Lead created
    Jul 9, 2022
  2. Won
    Aug 4, 2022
  3. Scheduled
    Aug 30, 2022
  4. Completed
    Sep 6, 2022