Command Palette
Search for a command to run...
Board
Open
JOB-1238Paid
Generator Transfer Switch — Silverbrook Car Wash
Silverbrook Car Wash · Building A — Front Office
$19,468
Generator Install
Scope of work
Set generator pad, run gas and electrical, commission unit. Existing materials removed and disposed of.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material20A Double-Pole Breaker | 9 ea | $36.97 | $332.73 |
| Material8 AWG THHN Copper — 500 ft spool | 3 spool | $484.38 | $1,453.14 |
| Material14/2 NM-B w/ Ground — 250 ft coil | 1 coil | $128.13 | $128.13 |
| Material200A Main Breaker Load Center, 40-space | 6 ea | $609.04 | $3,654.24 |
| MaterialAutomatic Transfer Switch, 200A | 2 ea | $1,553.66 | $3,107.32 |
| PermitPermit and inspection fees | 1 ea | $392.12 | $392.12 |
| LaborElectrical labour — generator install | 88.1 hr | $118.05 | $10,400.44 |
| Total | $19,468.12 | ||
Customer
Silverbrook Car Wash
Owen Cardoza
Project Manager
8063 Brightwater Ave
Safety Harbor, FL 34495
Safety Harbor, FL 34495
Assigned crew
Crew 4 — Power & Standby
Timeline
- Lead createdOct 10, 2025
- WonNov 4, 2025
- ScheduledNov 7, 2025
- CompletedNov 16, 2025