Parking Lot Lighting Retrofit — Stonegate Charter Academy
Stonegate Charter Academy · Primary Site
$35,056
Lighting Retrofit
Scope of work
Retrofit existing fixtures to LED throughout the specified areas. Existing materials removed and disposed of. All work per NEC and local amendments.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material8 AWG THHN Copper — 500 ft spool | 2 spool | $484.38 | $968.76 |
| Material4/0 AWG Aluminum SER Cable | 30 ft | $8.22 | $246.60 |
| MaterialLED High-Bay Fixture, 150W 5000K | 10 ea | $187.46 | $1,874.60 |
| EquipmentScissor lift rental | 6 day | $329.25 | $1,975.50 |
| LaborElectrical labour — lighting retrofit | 254.2 hr | $117.98 | $29,990.74 |
| Total | $35,056.20 | ||
Customer
Stonegate Charter Academy
Imani Dunmore
Project Manager
1881 Brightwater Ave
Riverview, FL 34355
Riverview, FL 34355
Assigned crew
Crew 1 — Commercial
Timeline
- Lead createdJul 11, 2023
- WonAug 2, 2023
- ScheduledAug 16, 2023
- CompletedAug 24, 2023