JOB-1248Paid

Generator Install + 100A ATS — Stonegate Charter Academy

Stonegate Charter Academy · Primary Site

$21,793
Generator Install

Scope of work

Install standby generator with automatic transfer switch. All work per NEC and local amendments. Customer to provide site access during working hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material20A Single-Pole Breaker4 ea$16.25$65
MaterialAir-Cooled Standby Generator, 22 kW1 ea$6,581.52$6,581.52
Material100A Main Breaker Load Center, 24-space6 ea$308.66$1,851.96
Material20A AFCI/GFCI Dual-Function Breaker2 ea$77.40$154.80
MaterialAutomatic Transfer Switch, 200A1 ea$1,553.66$1,553.66
Material50A Double-Pole Breaker2 ea$58.90$117.80
PermitPermit and inspection fees1 ea$255.63$255.63
LaborElectrical labour — generator install95 hr$118.02$11,212.32
Total$21,792.69

Activity

Notes on this job

  • EV
    Emmett VanceAug 13

    Inspection passed first time.

  • JA
    Junia AldermanJul 19

    Walked the site with the customer. Scope confirmed, no surprises.

  • AssistantJul 16

    Estimate drafted from the site notes and sent for review.

Customer

Open
Stonegate Charter Academy
Imani Dunmore
Project Manager
1881 Brightwater Ave
Riverview, FL 34355
Assigned crew
Crew 4 — Power & Standby

Timeline

  1. Lead created
    Jul 15, 2024
  2. Won
    Aug 8, 2024
  3. Scheduled
    Aug 23, 2024
  4. Completed
    Sep 1, 2024