Panel Upgrade — 100A Service + Surge Protection, Stonegate Charter Academy
Stonegate Charter Academy · Primary Site
$4,874
Panel Upgrade
Scope of work
Replace existing service panel and bring to current code. All work per NEC and local amendments. Existing materials removed and disposed of.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material12 AWG THHN Copper, White — 500 ft spool | 3 spool | $200.81 | $602.43 |
| Material20A Double-Pole Breaker | 1 ea | $36.97 | $36.97 |
| Material50A Double-Pole Breaker | 1 ea | $58.90 | $58.90 |
| Material12/3 NM-B w/ Ground — 250 ft coil | 2 coil | $253.23 | $506.46 |
| MaterialType 2 Whole-Home Surge Protective Device | 2 ea | $260.71 | $521.42 |
| PermitPermit and inspection fees | 1 ea | $314.42 | $314.42 |
| LaborElectrical labour — panel upgrade | 24 hr | $118.05 | $2,833.29 |
| Total | $4,873.89 | ||
Activity
Notes on this job
- JAJunia AldermanJul 11
Found existing wiring in worse shape than quoted. Flagged to customer.
Customer
Stonegate Charter Academy
Imani Dunmore
Project Manager
1881 Brightwater Ave
Riverview, FL 34355
Riverview, FL 34355
Assigned crew
Crew 4 — Power & Standby
Timeline
- Lead createdJul 4, 2023
- WonJul 13, 2023
- ScheduledJul 24, 2023
- CompletedJul 27, 2023