Board
JOB-1297Paid

Lighting Retrofit Phase 1 — Brightwater Parks Department

Brightwater Parks Department · Building B — Warehouse

$35,039
Lighting Retrofit

Scope of work

Retrofit existing fixtures to LED throughout the specified areas. All work per NEC and local amendments. Final walkthrough with customer before sign-off.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
MaterialLED High-Bay Fixture, 150W 5000K7 ea$187.46$1,312.22
MaterialLED Wall Pack, 80W w/ Photocell9 ea$140.22$1,261.98
Material14/2 NM-B w/ Ground — 250 ft coil1 coil$128.13$128.13
Material10 AWG THHN Copper, Red — 500 ft spool1 spool$305.45$305.45
EquipmentScissor lift rental6 day$409.57$2,457.42
LaborElectrical labour — lighting retrofit250.6 hr$118.01$29,574.04
Total$35,039.24

Job photos

2 from the field · click to enlarge

Activity

Notes on this job

  • AssistantJan 25

    Estimate drafted from the site notes and sent for review.

  • EV
    Emmett VanceJan 13

    Walked the site with the customer. Scope confirmed, no surprises.

Customer

Open
Brightwater Parks Department
Victor Whitaker
Facilities Director
3896 Pinecrest Commons
Plant City, FL 33962
Assigned crew
Crew 1 — Commercial

Timeline

  1. Lead created
    Jan 9, 2025
  2. Won
    Jan 31, 2025
  3. Scheduled
    Feb 12, 2025
  4. Completed
    Feb 17, 2025