Lighting Retrofit Phase 1 — Brightwater Parks Department
Brightwater Parks Department · Building B — Warehouse
$35,039
Lighting Retrofit
Scope of work
Retrofit existing fixtures to LED throughout the specified areas. All work per NEC and local amendments. Final walkthrough with customer before sign-off.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| MaterialLED High-Bay Fixture, 150W 5000K | 7 ea | $187.46 | $1,312.22 |
| MaterialLED Wall Pack, 80W w/ Photocell | 9 ea | $140.22 | $1,261.98 |
| Material14/2 NM-B w/ Ground — 250 ft coil | 1 coil | $128.13 | $128.13 |
| Material10 AWG THHN Copper, Red — 500 ft spool | 1 spool | $305.45 | $305.45 |
| EquipmentScissor lift rental | 6 day | $409.57 | $2,457.42 |
| LaborElectrical labour — lighting retrofit | 250.6 hr | $118.01 | $29,574.04 |
| Total | $35,039.24 | ||
Job photos
2 from the field · click to enlarge
Activity
Notes on this job
- AssistantJan 25
Estimate drafted from the site notes and sent for review.
- EVEmmett VanceJan 13
Walked the site with the customer. Scope confirmed, no surprises.
Customer
Brightwater Parks Department
Victor Whitaker
Facilities Director
3896 Pinecrest Commons
Plant City, FL 33962
Plant City, FL 33962
Assigned crew
Crew 1 — Commercial
Timeline
- Lead createdJan 9, 2025
- WonJan 31, 2025
- ScheduledFeb 12, 2025