Open
JOB-1308Paid
Low Voltage + Fire Alarm Rough-In — Kingfisher Marina
Kingfisher Marina · Front Office
$43,361
Fire Alarm / Low Voltage
Scope of work
Replace end-of-life devices and re-certify the system. Permit and inspection included.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material1/2 in EMT Set-Screw Connector | 8 ea | $2.07 | $16.56 |
| MaterialHorn/Strobe Notification Appliance | 3 ea | $97.58 | $292.74 |
| MaterialAddressable Fire Alarm Pull Station | 8 ea | $117.98 | $943.84 |
| Material2 in EMT Conduit — 10 ft stick | 6 ea | $65.21 | $391.26 |
| MaterialCat6A Riser Cable — 1000 ft box | 3 box | $354.35 | $1,063.05 |
| MaterialUnistrut Channel — 10 ft | 8 ea | $59.06 | $472.48 |
| PermitPermit and inspection fees | 1 ea | $445.42 | $445.42 |
| LaborElectrical labour — fire alarm / low voltage | 336.7 hr | $118.01 | $39,735.34 |
| Total | $43,360.69 | ||
Job photos
3 from the field · click to enlarge
Customer
Kingfisher Marina
Danielle Kirkland
Project Manager
1469 Egret Point Rd
Plant City, FL 34600
Plant City, FL 34600
Assigned crew
Crew 1 — Commercial
Timeline
- Lead createdMay 21, 2025
- WonJun 16, 2025
- ScheduledJul 11, 2025
- CompletedJul 20, 2025