EV Charger Install (8 ports) — Copperfield Medical Plaza

Copperfield Medical Plaza · Community Center

$10,496
EV Charger Install

Scope of work

Add EV charging capacity including panel work and conduit run. Permit and inspection included.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material400A Meter Main Combo, 42-space1 ea$1,721.36$1,721.36
Material100A Main Breaker Load Center, 24-space5 ea$308.66$1,543.30
LaborElectrical labour — ev charger install61.3 hr$117.97$7,231.78
Total$10,496.44

Job photos

3 from the field · click to enlarge

Activity

Notes on this job

  • EV
    Emmett VanceJun 12

    Materials staged at the shop, ready for Monday.

  • EV
    Emmett VanceJun 2

    Found existing wiring in worse shape than quoted. Flagged to customer.

  • AssistantMay 29

    Follow-up scheduled — no response to the estimate after 6 days.

Customer

Open
Copperfield Medical Plaza
Corey Fontaine
Facilities Director
4251 Sawgrass Reach Dr
Dunedin, FL 34674
Assigned crew
Crew 3 — Residential

Timeline

  1. Lead created
    May 27, 2024
  2. Won
    Jun 22, 2024
  3. Scheduled
    Jul 12, 2024
  4. Completed
    Jul 16, 2024