Command Palette
Search for a command to run...
Board
Open
JOB-1389Lost
Generator Transfer Switch — Ironwood Property Group
Ironwood Property Group · Building D — Storage Wing
$16,873
Generator Install
Scope of work
Install standby generator with automatic transfer switch. Includes as-built markup on completion.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material200A Main Breaker Load Center, 40-space | 6 ea | $609.04 | $3,654.24 |
| Material10 AWG THHN Copper, Red — 500 ft spool | 1 spool | $305.45 | $305.45 |
| Material20A AFCI/GFCI Dual-Function Breaker | 1 ea | $77.40 | $77.40 |
| PermitPermit and inspection fees | 1 ea | $466.34 | $466.34 |
| LaborElectrical labour — generator install | 104.8 hr | $118.03 | $12,369.71 |
| Total | $16,873.14 | ||
Customer
Ironwood Property Group
Tessa Grimaldi
Maintenance Supervisor
9690 Cypress Bend Ct
St. Petersburg, FL 33879
St. Petersburg, FL 33879
Timeline
- Lead createdJan 12, 2026
- Bid lostFeb 5, 2026
Lost: Price — went with a lower bid