Ground-Up Electrical — 5,000 sq ft Shell, Bayshore Auto Center

Bayshore Auto Center · Community Center

$77,196
New Construction Rough-In

Scope of work

Furnish and install all electrical for the shell and core. Existing materials removed and disposed of. All work per NEC and local amendments.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
MaterialType 2 Whole-Home Surge Protective Device4 ea$260.71$1,042.84
MaterialAutomatic Transfer Switch, 200A3 ea$1,553.66$4,660.98
PermitPermit and inspection fees1 ea$426.89$426.89
LaborElectrical labour — new construction rough-in602.2 hr$118.01$71,065.36
Total$77,196.07

Activity

Notes on this job

  • JA
    Junia AldermanDec 28

    Found existing wiring in worse shape than quoted. Flagged to customer.

  • AssistantDec 17

    Follow-up scheduled — no response to the estimate after 6 days.

Customer

Open
Bayshore Auto Center
Arturo Castellanos
Property Manager
8325 Heron Cove Ct
Temple Terrace, FL 33753
Assigned crew
Crew 1 — Commercial

Timeline

  1. Lead created
    Dec 10, 2021
  2. Won
    Jan 4, 2022
  3. Scheduled
    Jan 10, 2022
  4. Completed
    Jan 19, 2022