JOB-1442Paid

EV Charger Install (4 ports) — Northline Public Library

Northline Public Library · Primary Site

$9,685
EV Charger Install

Scope of work

Install Level 2 EV charging equipment with dedicated circuit. Existing materials removed and disposed of.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material8 AWG THHN Copper — 500 ft spool1 spool$484.38$484.38
Material14/2 NM-B w/ Ground — 250 ft coil2 coil$128.13$256.26
LaborElectrical labour — ev charger install75.8 hr$118$8,944.70
Total$9,685.34

Customer

Open
Northline Public Library
Tessa Radcliffe
Maintenance Supervisor
148 Sable Ridge Blvd
Oldsmar, FL 33696
Assigned crew
Crew 3 — Residential

Timeline

  1. Lead created
    Dec 20, 2024
  2. Won
    Jan 7, 2025
  3. Scheduled
    Jan 31, 2025
  4. Completed
    Feb 9, 2025

Documents