2

Command Palette

Search for a command to run...

Board
JOB-1477Paid

Lighting Retrofit Phase 2 — Northline HOA

Northline HOA · Primary Site

$47,382
Lighting Retrofit

Scope of work

Replace fixtures, install controls, and verify light levels. Permit and inspection included.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material12 AWG THHN Copper, Black — 500 ft spool2 spool$200.81$401.62
Material10 AWG THHN Copper, Red — 500 ft spool1 spool$305.45$305.45
MaterialLED Troffer 2x4, 40W 4000K8 ea$109.89$879.12
Material6 in LED Recessed Downlight, Canless10 ea$29.36$293.60
MaterialLED Wall Pack, 80W w/ Photocell9 ea$140.22$1,261.98
EquipmentScissor lift rental4 day$298.55$1,194.20
LaborElectrical labour — lighting retrofit364.8 hr$118$43,045.80
Total$47,381.77

Customer

Open
Northline HOA
Nadia Ivory
Property Manager
9556 Harborlight Way
Oldsmar, FL 34648
Assigned crew
Crew 1 — Commercial

Timeline

  1. Lead created
    May 2, 2023
  2. Won
    May 21, 2023
  3. Scheduled
    May 25, 2023
  4. Completed
    Jun 2, 2023

Documents