JOB-1500Paid

EV Charging Expansion Phase 2 — Oakfield School District

Oakfield School District · Pump House

$8,261
EV Charger Install

Scope of work

Add EV charging capacity including panel work and conduit run. Work to be performed outside business hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material20A AFCI/GFCI Dual-Function Breaker1 ea$77.40$77.40
MaterialAutomatic Transfer Switch, 200A1 ea$1,553.66$1,553.66
Material12/3 NM-B w/ Ground — 250 ft coil1 coil$253.23$253.23
LaborElectrical labour — ev charger install54 hr$118.08$6,376.28
Total$8,260.57

Job photos

2 from the field · click to enlarge

Customer

Open
Oakfield School District
Junia Underhill
Business Manager
9304 Cypress Bend Ct
Seminole, FL 34306
Assigned crew
Crew 4 — Power & Standby

Timeline

  1. Lead created
    Oct 28, 2020
  2. Won
    Nov 26, 2020
  3. Scheduled
    Dec 12, 2020
  4. Completed
    Dec 15, 2020