3

Command Palette

Search for a command to run...

Board
JOB-1511Paid

EV Charger Install (17 ports) — Clearpoint Bowling Center

Clearpoint Bowling Center · Parking Structure

$9,020
EV Charger Install

Scope of work

Install Level 2 EV charging equipment with dedicated circuit. Work to be performed outside business hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
MaterialAutomatic Transfer Switch, 200A2 ea$1,553.66$3,107.32
Material12 AWG THHN Copper, White — 500 ft spool3 spool$200.81$602.43
Material4/0 AWG Aluminum SER Cable11 ft$8.22$90.42
LaborElectrical labour — ev charger install44.2 hr$118.08$5,219.35
Total$9,019.52

Job photos

2 from the field · click to enlarge

Customer

Open
Clearpoint Bowling Center
Bethany Sandoval
Business Manager
2818 Lakemont Loop
Clearwater, FL 34502
Assigned crew
Crew 4 — Power & Standby

Timeline

  1. Lead created
    May 10, 2026
  2. Won
    May 24, 2026
  3. Scheduled
    Jun 4, 2026
  4. Completed
    Jun 6, 2026

Documents