JOB-1546Paid
Generator Transfer Switch — Brightwater Fellowship Church
Brightwater Fellowship Church · Warehouse
$23,712
Generator Install
Scope of work
Set generator pad, run gas and electrical, commission unit. Work to be performed outside business hours. Customer to provide site access during working hours.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material400A Meter Main Combo, 42-space | 6 ea | $1,721.36 | $10,328.16 |
| Material14/2 NM-B w/ Ground — 250 ft coil | 3 coil | $128.13 | $384.39 |
| Material50A Double-Pole Breaker | 1 ea | $58.90 | $58.90 |
| Material4/0 AWG Aluminum SER Cable | 14 ft | $8.22 | $115.08 |
| PermitPermit and inspection fees | 1 ea | $364.39 | $364.39 |
| LaborElectrical labour — generator install | 105.6 hr | $118 | $12,460.91 |
| Total | $23,711.83 | ||
Job photos
4 from the field · click to enlarge
Customer
Brightwater Fellowship Church
Grant Sandoval
Operations Manager
1280 Sable Ridge Blvd
Lutz, FL 33643
Lutz, FL 33643
Assigned crew
Crew 4 — Power & Standby
Timeline
- Lead createdMar 28, 2023
- WonApr 20, 2023
- ScheduledMay 8, 2023
- CompletedMay 14, 2023