EV Charging Expansion Phase 2 — Silverbrook Public Library

Silverbrook Public Library · Building A — Pump House

$4,539
EV Charger Install

Scope of work

Add EV charging capacity including panel work and conduit run. Customer to provide site access during working hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material20A Double-Pole Breaker6 ea$36.97$221.82
Material20A Single-Pole Breaker5 ea$16.25$81.25
Material12 AWG THHN Copper, Black — 500 ft spool2 spool$200.81$401.62
MaterialType 2 Whole-Home Surge Protective Device3 ea$260.71$782.13
LaborElectrical labour — ev charger install25.9 hr$117.85$3,052.25
Total$4,539.07

Job photos

3 from the field · click to enlarge

Activity

Notes on this job

  • JA
    Junia AldermanJan 3

    Permit submitted. Waiting on the county.

Customer

Open
Silverbrook Public Library
Yolanda Ashford
Facilities Director
353 Pinecrest Commons
Clearwater, FL 33683
Assigned crew
Crew 1 — Commercial

Timeline

  1. Lead created
    Dec 23, 2023
  2. Won
    Jan 8, 2024
  3. Scheduled
    Jan 12, 2024
  4. Completed
    Jan 15, 2024