JOB-1556Estimate Sent

Partial Rewire — Knob & Tube Removal, Sable Ridge Marina

Sable Ridge Marina · Community Center

$15,851
Rewire

Scope of work

Replace branch circuit wiring and devices throughout. Work to be performed outside business hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material50A Double-Pole Breaker5 ea$58.90$294.50
Material200A Main Breaker Load Center, 40-space6 ea$609.04$3,654.24
Material1/2 in EMT Set-Screw Connector5 ea$2.07$10.35
Material3/4 in Schedule 40 PVC — 10 ft stick4 ea$10.61$42.44
PermitPermit and inspection fees1 ea$291.90$291.90
LaborElectrical labour — rewire97.9 hr$118.06$11,557.76
Total$15,851.19