Open
JOB-1557Paid
Parking Lot Lighting Retrofit — Sable Ridge Marina
Sable Ridge Marina · Unit Block
$48,814
Lighting Retrofit
Scope of work
Replace fixtures, install controls, and verify light levels. Existing materials removed and disposed of. All work per NEC and local amendments.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material12 AWG THHN Copper, Black — 500 ft spool | 2 spool | $200.81 | $401.62 |
| MaterialLED High-Bay Fixture, 150W 5000K | 12 ea | $187.46 | $2,249.52 |
| MaterialLED Parking Lot Fixture, 240W Type III | 12 ea | $541.10 | $6,493.20 |
| Material12 AWG THHN Copper, White — 500 ft spool | 2 spool | $200.81 | $401.62 |
| Material10 AWG THHN Copper, Red — 500 ft spool | 3 spool | $305.45 | $916.35 |
| EquipmentScissor lift rental | 4 day | $418.56 | $1,674.24 |
| LaborElectrical labour — lighting retrofit | 310.8 hr | $118.01 | $36,677.35 |
| Total | $48,813.90 | ||
Job photos
4 from the field · click to enlarge
Customer
Sable Ridge Marina
Silas Dunmore
Property Manager
4633 Copperfield Row
Safety Harbor, FL 34640
Safety Harbor, FL 34640
Assigned crew
Crew 1 — Commercial
Timeline
- Lead createdOct 13, 2022
- WonNov 10, 2022
- ScheduledNov 30, 2022
- CompletedDec 5, 2022