Generator Install + 400A ATS — Silverbrook Public Library

Silverbrook Public Library · Maintenance Shop

$25,593
Generator Install

Scope of work

Set generator pad, run gas and electrical, commission unit. All work per NEC and local amendments. Existing materials removed and disposed of.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
MaterialLevel 2 EV Charger, 48A Hardwired4 ea$862.22$3,448.88
Material20A AFCI/GFCI Dual-Function Breaker1 ea$77.40$77.40
PermitPermit and inspection fees1 ea$120.52$120.52
LaborElectrical labour — generator install186 hr$117.99$21,946.30
Total$25,593.10

Job photos

4 from the field · click to enlarge

Customer

Open
Silverbrook Public Library
Yolanda Ashford
Facilities Director
2115 Lakemont Loop
Dunedin, FL 34625
Assigned crew
Crew 4 — Power & Standby

Timeline

  1. Lead created
    Jul 6, 2024
  2. Won
    Jul 22, 2024
  3. Scheduled
    Jul 29, 2024
  4. Completed
    Aug 1, 2024