2

Command Palette

Search for a command to run...

Board
JOB-1567Paid

Standby Generator Install — 22 kW, Oakfield Apartments

Oakfield Apartments · Main Building

$21,509
Generator Install

Scope of work

Set generator pad, run gas and electrical, commission unit. Permit and inspection included.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material6 AWG Bare Copper Ground326 ft$2.92$951.92
Material20A AFCI/GFCI Dual-Function Breaker9 ea$77.40$696.60
Material100A Main Breaker Load Center, 24-space6 ea$308.66$1,851.96
Material200A Main Breaker Load Center, 40-space9 ea$609.04$5,481.36
MaterialLevel 2 EV Charger, 48A Hardwired1 ea$862.22$862.22
PermitPermit and inspection fees1 ea$456.44$456.44
LaborElectrical labour — generator install95 hr$117.98$11,208.34
Total$21,508.84

Customer

Open
Oakfield Apartments
Silas Delacroix
Property Manager
6634 Tidewater Crossing
Lutz, FL 33603
Assigned crew
Crew 4 — Power & Standby

Timeline

  1. Lead created
    Oct 10, 2025
  2. Won
    Oct 21, 2025
  3. Scheduled
    Oct 27, 2025
  4. Completed
    Nov 1, 2025

Documents