Scope of work
Complete electrical rough-in per approved drawings. Includes as-built markup on completion. Work to be performed outside business hours.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material20A AFCI/GFCI Dual-Function Breaker | 6 ea | $77.40 | $464.40 |
| Material2 in EMT Conduit — 10 ft stick | 12 ea | $65.21 | $782.52 |
| MaterialLED Parking Lot Fixture, 240W Type III | 4 ea | $541.10 | $2,164.40 |
| Material12 AWG THHN Copper, Black — 500 ft spool | 1 spool | $200.81 | $200.81 |
| MaterialLevel 2 EV Charger, 48A Hardwired | 9 ea | $862.22 | $7,759.98 |
| Material14/2 NM-B w/ Ground — 250 ft coil | 3 coil | $128.13 | $384.39 |
| PermitPermit and inspection fees | 1 ea | $167.72 | $167.72 |
| LaborElectrical labour — new construction rough-in | 696.9 hr | $117.99 | $82,230.34 |
| Total | $94,154.56 | ||
Job photos
4 from the field · click to enlarge
Customer
Kingfisher Car Wash
Marisol Hollingsworth
Maintenance Supervisor
3374 Heron Cove Ct
Tampa, FL 34455
Tampa, FL 34455
Assigned crew
Crew 1 — Commercial
Timeline
- Lead createdJul 4, 2022
- WonJul 20, 2022
- ScheduledJul 25, 2022
- CompletedJul 30, 2022