EV Charging Expansion Phase 3 — Whitecap Estates
Whitecap Estates · Loading Dock
$7,334
EV Charger Install
Scope of work
Add EV charging capacity including panel work and conduit run. Final walkthrough with customer before sign-off.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material400A Meter Main Combo, 42-space | 1 ea | $1,721.36 | $1,721.36 |
| Material20A Double-Pole Breaker | 6 ea | $36.97 | $221.82 |
| Material14/2 NM-B w/ Ground — 250 ft coil | 3 coil | $128.13 | $384.39 |
| Material50A Double-Pole Breaker | 2 ea | $58.90 | $117.80 |
| Material100A Main Breaker Load Center, 24-space | 1 ea | $308.66 | $308.66 |
| LaborElectrical labour — ev charger install | 38.8 hr | $118.05 | $4,580.21 |
| Total | $7,334.24 | ||
Job photos
3 from the field · click to enlarge
Activity
Notes on this job
- EVEmmett VanceAug 14
Permit submitted. Waiting on the county.
- JAJunia AldermanAug 1
Found existing wiring in worse shape than quoted. Flagged to customer.
Customer
Whitecap Estates
Silas Mercer
Property Manager
4731 Brightwater Ave
Plant City, FL 34402
Plant City, FL 34402
Assigned crew
Crew 4 — Power & Standby
Timeline
- Lead createdJul 22, 2022
- WonAug 11, 2022
- ScheduledSep 2, 2022
- CompletedSep 11, 2022