JOB-1693Paid

Ground-Up Electrical — 9,000 sq ft Shell, Northline Auto Center

Northline Auto Center · Storage Wing

$54,231
New Construction Rough-In

Scope of work

Complete electrical rough-in per approved drawings. Final walkthrough with customer before sign-off. Permit and inspection included.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material20A Commercial Duplex Receptacle, Spec Grade4 ea$10.40$41.60
Material14/2 NM-B w/ Ground — 250 ft coil3 coil$128.13$384.39
Material20A Single-Pole Breaker2 ea$16.25$32.50
Material3/4 in EMT Conduit — 10 ft stick8 ea$22.79$182.32
PermitPermit and inspection fees1 ea$239.90$239.90
LaborElectrical labour — new construction rough-in452.1 hr$118.01$53,350.12
Total$54,230.83

Job photos

4 from the field · click to enlarge

Activity

Notes on this job

  • AssistantJan 20

    Invoice prepared and queued for approval.

  • JA
    Junia AldermanJan 17

    Walked the site with the customer. Scope confirmed, no surprises.

Customer

Open
Northline Auto Center
Delphine Langford
Facilities Director
6209 Ironwood Commerce Dr
Largo, FL 34104
Assigned crew
Crew 1 — Commercial

Timeline

  1. Lead created
    Dec 25, 2020
  2. Won
    Jan 17, 2021
  3. Scheduled
    Feb 8, 2021
  4. Completed
    Feb 17, 2021

Documents