JOB-1699Invoiced

EV Charger Install (11 ports) — Northline Auto Center

Northline Auto Center · Storage Wing

$8,466
EV Charger Install

Scope of work

Install Level 2 EV charging equipment with dedicated circuit. Customer to provide site access during working hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material400A Meter Main Combo, 42-space1 ea$1,721.36$1,721.36
Material14/2 NM-B w/ Ground — 250 ft coil1 coil$128.13$128.13
Material20A AFCI/GFCI Dual-Function Breaker9 ea$77.40$696.60
LaborElectrical labour — ev charger install50.2 hr$117.92$5,919.60
Total$8,465.69

Job photos

3 from the field · click to enlarge

Customer

Open
Northline Auto Center
Delphine Langford
Facilities Director
6209 Ironwood Commerce Dr
Largo, FL 34104
Assigned crew
Crew 4 — Power & Standby

Timeline

  1. Lead created
    Jul 11, 2026
  2. Won
    Jul 29, 2026
  3. Scheduled
    Aug 11, 2026
  4. Completed
    Aug 14, 2026