Panel Upgrade — 200A Service, Copperfield Estates
Copperfield Estates · Parking Structure
$4,843
Panel Upgrade
Scope of work
Remove obsolete panel and install new load center. Customer to provide site access during working hours.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material50A Double-Pole Breaker | 1 ea | $58.90 | $58.90 |
| Material200A Main Breaker Load Center, 40-space | 2 ea | $609.04 | $1,218.08 |
| Material4/0 AWG Aluminum SER Cable | 30 ft | $8.22 | $246.60 |
| PermitPermit and inspection fees | 1 ea | $411.82 | $411.82 |
| LaborElectrical labour — panel upgrade | 24.6 hr | $118.20 | $2,907.62 |
| Total | $4,843.02 | ||
Customer
Copperfield Estates
Theo Everly
Community Manager
9317 Fernbank Trl
Lutz, FL 34010
Lutz, FL 34010
Timeline
- Lead createdMay 2, 2023
- Bid lostMay 29, 2023
Lost: Price — went with a lower bid