EV Charging Expansion Phase 1 — Marsh Landing Townhomes

Marsh Landing Townhomes · Building A — Community Center

$8,713
EV Charger Install

Scope of work

Install Level 2 EV charging equipment with dedicated circuit. Final walkthrough with customer before sign-off. All work per NEC and local amendments.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material4/0 AWG Aluminum SER Cable60 ft$8.22$493.20
Material8 AWG THHN Copper — 500 ft spool2 spool$484.38$968.76
LaborElectrical labour — ev charger install61.5 hr$117.91$7,251.28
Total$8,713.24

Customer

Open
Marsh Landing Townhomes
Desmond Whitaker
Property Manager
5539 Brightwater Ave
St. Petersburg, FL 33647
Assigned crew
Crew 3 — Residential

Timeline

  1. Lead created
    Mar 10, 2024
  2. Won
    Mar 27, 2024
  3. Scheduled
    Apr 22, 2024
  4. Completed
    May 1, 2024