Generator Transfer Switch — Eastgate Property Group

Eastgate Property Group · Storage Wing

$15,746
Generator Install

Scope of work

Install standby generator with automatic transfer switch. All work per NEC and local amendments. Existing materials removed and disposed of.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material50A Double-Pole Breaker8 ea$58.90$471.20
Material200A Main Breaker Load Center, 40-space2 ea$609.04$1,218.08
Material20A AFCI/GFCI Dual-Function Breaker12 ea$77.40$928.80
Material20A Double-Pole Breaker3 ea$36.97$110.91
MaterialAutomatic Transfer Switch, 200A3 ea$1,553.66$4,660.98
MaterialType 2 Whole-Home Surge Protective Device3 ea$260.71$782.13
PermitPermit and inspection fees1 ea$128.65$128.65
LaborElectrical labour — generator install63.1 hr$117.99$7,445.19
Total$15,745.94

Activity

Notes on this job

  • JA
    Junia AldermanMay 13

    Found existing wiring in worse shape than quoted. Flagged to customer.

Customer

Open
Eastgate Property Group
Nadia Winthrop
Regional Manager
7884 Copperfield Row
Palm Harbor, FL 34625
Assigned crew
Crew 4 — Power & Standby

Timeline

  1. Lead created
    May 4, 2026
  2. Won
    May 29, 2026
  3. Scheduled
    Jun 16, 2026
  4. Completed
    Jun 23, 2026