Generator Transfer Switch — Eastgate Property Group
Eastgate Property Group · Storage Wing
$15,746
Generator Install
Scope of work
Install standby generator with automatic transfer switch. All work per NEC and local amendments. Existing materials removed and disposed of.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material50A Double-Pole Breaker | 8 ea | $58.90 | $471.20 |
| Material200A Main Breaker Load Center, 40-space | 2 ea | $609.04 | $1,218.08 |
| Material20A AFCI/GFCI Dual-Function Breaker | 12 ea | $77.40 | $928.80 |
| Material20A Double-Pole Breaker | 3 ea | $36.97 | $110.91 |
| MaterialAutomatic Transfer Switch, 200A | 3 ea | $1,553.66 | $4,660.98 |
| MaterialType 2 Whole-Home Surge Protective Device | 3 ea | $260.71 | $782.13 |
| PermitPermit and inspection fees | 1 ea | $128.65 | $128.65 |
| LaborElectrical labour — generator install | 63.1 hr | $117.99 | $7,445.19 |
| Total | $15,745.94 | ||
Activity
Notes on this job
- JAJunia AldermanMay 13
Found existing wiring in worse shape than quoted. Flagged to customer.
Customer
Eastgate Property Group
Nadia Winthrop
Regional Manager
7884 Copperfield Row
Palm Harbor, FL 34625
Palm Harbor, FL 34625
Assigned crew
Crew 4 — Power & Standby
Timeline
- Lead createdMay 4, 2026
- WonMay 29, 2026
- ScheduledJun 16, 2026
- CompletedJun 23, 2026