JOB-1925Paid

EV Charging Expansion Phase 3 — Eastgate Property Group

Eastgate Property Group · Maintenance Shop

$10,923
EV Charger Install

Scope of work

Add EV charging capacity including panel work and conduit run. Customer to provide site access during working hours. Final walkthrough with customer before sign-off.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material50A Double-Pole Breaker5 ea$58.90$294.50
Material6 AWG Bare Copper Ground368 ft$2.92$1,074.56
LaborElectrical labour — ev charger install81 hr$117.95$9,553.68
Total$10,922.74

Job photos

3 from the field · click to enlarge

Customer

Open
Eastgate Property Group
Nadia Winthrop
Regional Manager
1919 Sable Ridge Blvd
Seminole, FL 34432
Assigned crew
Crew 3 — Residential

Timeline

  1. Lead created
    Mar 11, 2022
  2. Won
    Mar 30, 2022
  3. Scheduled
    Apr 25, 2022
  4. Completed
    Apr 28, 2022