Command Palette
Search for a command to run...
Board
Open
JOB-2027Paid
Generator Transfer Switch — Copperfield Condominium Association
Copperfield Condominium Association · Building C — Pump House
$25,907
Generator Install
Scope of work
Set generator pad, run gas and electrical, commission unit. Final walkthrough with customer before sign-off.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material100A Main Breaker Load Center, 24-space | 2 ea | $308.66 | $617.32 |
| Material6 AWG Bare Copper Ground | 333 ft | $2.92 | $972.36 |
| MaterialAir-Cooled Standby Generator, 22 kW | 1 ea | $6,581.52 | $6,581.52 |
| Material50A Double-Pole Breaker | 9 ea | $58.90 | $530.10 |
| Material8 AWG THHN Copper — 500 ft spool | 1 spool | $484.38 | $484.38 |
| PermitPermit and inspection fees | 1 ea | $314.15 | $314.15 |
| LaborElectrical labour — generator install | 139 hr | $118.03 | $16,406.80 |
| Total | $25,906.63 | ||
Job photos
3 from the field · click to enlarge
Customer
Copperfield Condominium Association
Rosalind Thackeray
Property Manager
9206 Ironwood Commerce Dr
Palm Harbor, FL 34180
Palm Harbor, FL 34180
Assigned crew
Crew 4 — Power & Standby
Timeline
- Lead createdJul 24, 2023
- WonAug 15, 2023
- ScheduledSep 8, 2023
- CompletedSep 10, 2023