Standby Generator Install — 22 kW, Pinecrest Senior Living
Pinecrest Senior Living · Building D — Community Center
$13,636
Generator Install
Scope of work
Install standby generator with automatic transfer switch. Work to be performed outside business hours. Includes as-built markup on completion.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material400A Meter Main Combo, 42-space | 3 ea | $1,721.36 | $5,164.08 |
| Material10 AWG THHN Copper, Red — 500 ft spool | 2 spool | $305.45 | $610.90 |
| Material200A Main Breaker Load Center, 40-space | 1 ea | $609.04 | $609.04 |
| Material50A Double-Pole Breaker | 3 ea | $58.90 | $176.70 |
| Material6 AWG Bare Copper Ground | 17 ft | $2.92 | $49.64 |
| PermitPermit and inspection fees | 1 ea | $164.82 | $164.82 |
| LaborElectrical labour — generator install | 58.1 hr | $118.09 | $6,861.30 |
| Total | $13,636.48 | ||
Activity
Notes on this job
- AssistantJul 19
Follow-up scheduled — no response to the estimate after 6 days.
Customer
Pinecrest Senior Living
Corey Mercer
Regional Manager
8662 Sawgrass Reach Dr
Lutz, FL 34666
Lutz, FL 34666
Assigned crew
Crew 4 — Power & Standby
Timeline
- Lead createdJul 19, 2021
- WonJul 31, 2021
- ScheduledAug 16, 2021