JOB-2273Estimate Sent

Service Upgrade — 200A Meter Main, Clearpoint HOA

Clearpoint HOA · Loading Dock

$3,987
Panel Upgrade

Scope of work

Upgrade electrical service, including meter main and grounding. Customer to provide site access during working hours. All work per NEC and local amendments.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material50A Double-Pole Breaker3 ea$58.90$176.70
Material200A Main Breaker Load Center, 40-space2 ea$609.04$1,218.08
Material12/3 NM-B w/ Ground — 250 ft coil1 coil$253.23$253.23
PermitPermit and inspection fees1 ea$304.90$304.90
LaborElectrical labour — panel upgrade17.2 hr$118.25$2,033.92
Total$3,986.83

Activity

Notes on this job

  • AssistantAug 6

    Estimate drafted from the site notes and sent for review.

  • JA
    Junia AldermanJul 25

    Customer asked to push a week. Rescheduled.

Customer

Open
Clearpoint HOA
Sloane Grimaldi
Community Manager
2934 Tidewater Crossing
Seminole, FL 34110

Timeline

  1. Lead created
    Jul 12, 2026

Documents