EV Charger Install — Level 2, 48A, Eastgate Property Management
Eastgate Property Management · Building B — Maintenance Shop
$7,211
EV Charger Install
Scope of work
Install Level 2 EV charging equipment with dedicated circuit. Permit and inspection included. Final walkthrough with customer before sign-off.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material20A AFCI/GFCI Dual-Function Breaker | 6 ea | $77.40 | $464.40 |
| Material200A Main Breaker Load Center, 40-space | 2 ea | $609.04 | $1,218.08 |
| LaborElectrical labour — ev charger install | 46.8 hr | $118.13 | $5,528.29 |
| Total | $7,210.77 | ||
Customer
Eastgate Property Management
Emmett Alderman
Maintenance Coordinator
308 Copperfield Row
Safety Harbor, FL 34425
Safety Harbor, FL 34425
Timeline
- Lead createdAug 24, 2023
- Bid lostSep 6, 2023
Lost: Budget not approved this cycle