2

Command Palette

Search for a command to run...

Board
JOB-2423Paid

Lighting Retrofit Phase 2 — Heron Cove Condominium Association

Heron Cove Condominium Association · Parking Structure

$23,698
Lighting Retrofit

Scope of work

Replace fixtures, install controls, and verify light levels. Customer to provide site access during working hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material4/0 AWG Aluminum SER Cable190 ft$8.22$1,561.80
MaterialLED Troffer 2x4, 40W 4000K1 ea$109.89$109.89
Material12 AWG THHN Copper, Black — 500 ft spool2 spool$200.81$401.62
EquipmentScissor lift rental4 day$336.62$1,346.48
LaborElectrical labour — lighting retrofit171.9 hr$117.97$20,278.64
Total$23,698.43

Job photos

4 from the field · click to enlarge

Customer

Open
Heron Cove Condominium Association
Desmond Jessup
Board President
9762 Heron Cove Ct
St. Petersburg, FL 34001
Assigned crew
Crew 1 — Commercial

Timeline

  1. Lead created
    Jul 15, 2022
  2. Won
    Aug 6, 2022
  3. Scheduled
    Aug 11, 2022
  4. Completed
    Aug 11, 2022

Documents