JOB-2650Paid

Service Upgrade — 400A Meter Main, Marisol Quintero

Marisol Quintero · Primary Site

$5,230
Panel Upgrade

Scope of work

Remove obsolete panel and install new load center. Customer to provide site access during working hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material12/3 NM-B w/ Ground — 250 ft coil3 coil$253.23$759.69
Material200A Main Breaker Load Center, 40-space1 ea$609.04$609.04
Material20A Single-Pole Breaker12 ea$16.25$195
PermitPermit and inspection fees1 ea$373.27$373.27
LaborElectrical labour — panel upgrade27.9 hr$118.04$3,293.20
Total$5,230.20

Job photos

3 from the field · click to enlarge

Customer

Open
Marisol Quintero
Marisol Quintero
Tenant
7679 Sable Ridge Blvd
Plant City, FL 34411
Assigned crew
Crew 4 — Power & Standby

Timeline

  1. Lead created
    Mar 28, 2026
  2. Won
    Apr 15, 2026
  3. Scheduled
    May 11, 2026
  4. Completed
    May 15, 2026

Documents