Panel Upgrade — 200A Service + Surge Protection, Sloane Beckett

Sloane Beckett · Primary Site

$3,549
Panel Upgrade

Scope of work

Remove obsolete panel and install new load center. All work per NEC and local amendments.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material12/3 NM-B w/ Ground — 250 ft coil3 coil$253.23$759.69
Material50A Double-Pole Breaker9 ea$58.90$530.10
PermitPermit and inspection fees1 ea$382.01$382.01
LaborElectrical labour — panel upgrade15.9 hr$118.07$1,877.29
Total$3,549.09