JOB-3168Lost

Panel Upgrade — 400A Service, Marcus Alderman — Annex

Marcus Alderman — Annex · Primary Site

$5,223
Panel Upgrade

Scope of work

Remove obsolete panel and install new load center. Includes as-built markup on completion. Final walkthrough with customer before sign-off.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material100A Main Breaker Load Center, 24-space2 ea$308.66$617.32
Material14/2 NM-B w/ Ground — 250 ft coil2 coil$128.13$256.26
Material50A Double-Pole Breaker4 ea$58.90$235.60
Material12 AWG THHN Copper, White — 500 ft spool1 spool$200.81$200.81
Material4/0 AWG Aluminum SER Cable91 ft$8.22$748.02
PermitPermit and inspection fees1 ea$426.14$426.14
LaborElectrical labour — panel upgrade23.2 hr$118.04$2,738.45
Total$5,222.60

Activity

Notes on this job

  • EV
    Emmett VanceApr 15

    Found existing wiring in worse shape than quoted. Flagged to customer.

  • JA
    Junia AldermanApr 9

    Inspection passed first time.

  • JA
    Junia AldermanMar 21

    Materials staged at the shop, ready for Monday.

Customer

Open
Marcus Alderman — Annex
Marcus Alderman — Annex
Tenant
9191 Stonegate Cir
Wesley Chapel, FL 34464

Timeline

  1. Lead created
    Mar 17, 2023
  2. Bid lost
    Apr 8, 2023

Lost: Budget not approved this cycle