Ground-Up Electrical — 3,000 sq ft Shell, Tidewater Bowling Center

Tidewater Bowling Center · Primary Site

$106,511
New Construction Rough-In

Scope of work

Complete electrical rough-in per approved drawings. Includes as-built markup on completion. Final walkthrough with customer before sign-off.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material12/3 NM-B w/ Ground — 250 ft coil2 coil$253.23$506.46
MaterialLED Wall Pack, 80W w/ Photocell2 ea$140.22$280.44
MaterialLED Exit Sign w/ Battery Backup12 ea$66.07$792.84
Material4 in Square Metal Box w/ Mud Ring10 ea$6.54$65.40
Material1/2 in EMT Set-Screw Connector7 ea$2.07$14.49
PermitPermit and inspection fees1 ea$324.75$324.75
LaborElectrical labour — new construction rough-in885.8 hr$118$104,526.16
Total$106,510.54

Activity

Notes on this job

  • EV
    Emmett VanceJun 9

    Inspection passed first time.

  • EV
    Emmett VanceMay 25

    Found existing wiring in worse shape than quoted. Flagged to customer.

Customer

Open
Tidewater Bowling Center
Nadia Fontaine
Business Manager
6790 Cypress Bend Ct
Palm Harbor, FL 34190
Assigned crew
Crew 1 — Commercial

Timeline

  1. Lead created
    May 14, 2026
  2. Won
    Jun 8, 2026
  3. Scheduled
    Jun 29, 2026
  4. Completed
    Jul 1, 2026