JOB-1381Lost

EV Charging Expansion Phase 2 — Tidewater Bowling Center

Tidewater Bowling Center · Primary Site

$9,233
EV Charger Install

Scope of work

Add EV charging capacity including panel work and conduit run. Existing materials removed and disposed of.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material100A Main Breaker Load Center, 24-space9 ea$308.66$2,777.94
Material12 AWG THHN Copper, White — 500 ft spool1 spool$200.81$200.81
LaborElectrical labour — ev charger install53 hr$118$6,253.77
Total$9,232.52

Activity

Notes on this job

  • AssistantAug 8

    Estimate drafted from the site notes and sent for review.

Customer

Open
Tidewater Bowling Center
Nadia Fontaine
Business Manager
6790 Cypress Bend Ct
Palm Harbor, FL 34190

Timeline

  1. Lead created
    Jul 14, 2025
  2. Bid lost
    Jul 29, 2025

Lost: Price — went with a lower bid