EV Charger Install — Level 2, 48A, Copperfield Apartments

Copperfield Apartments · Annex

$8,561
EV Charger Install

Scope of work

Install Level 2 EV charging equipment with dedicated circuit. Includes as-built markup on completion. All work per NEC and local amendments.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material14/2 NM-B w/ Ground — 250 ft coil1 coil$128.13$128.13
Material20A Single-Pole Breaker6 ea$16.25$97.50
MaterialAutomatic Transfer Switch, 200A2 ea$1,553.66$3,107.32
Material4/0 AWG Aluminum SER Cable45 ft$8.22$369.90
LaborElectrical labour — ev charger install41.2 hr$117.92$4,858.12
Total$8,560.97

Job photos

3 from the field · click to enlarge

Activity

Notes on this job

  • EV
    Emmett VanceJun 3

    Found existing wiring in worse shape than quoted. Flagged to customer.

Customer

Open
Copperfield Apartments
Grant Dunmore
Regional Manager
5970 Copperfield Row
St. Petersburg, FL 34413
Assigned crew
Crew 3 — Residential

Timeline

  1. Lead created
    May 6, 2023
  2. Won
    May 19, 2023
  3. Scheduled
    Jun 2, 2023
  4. Completed
    Jun 2, 2023