JOB-1846Lost

EV Charger Install — Level 2, 48A, Marsh Landing Townhomes

Marsh Landing Townhomes · Storage Wing

$4,933
EV Charger Install

Scope of work

Add EV charging capacity including panel work and conduit run. Includes as-built markup on completion. Work to be performed outside business hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material12 AWG THHN Copper, Black — 500 ft spool2 spool$200.81$401.62
Material10 AWG THHN Copper, Red — 500 ft spool2 spool$305.45$610.90
Material50A Double-Pole Breaker8 ea$58.90$471.20
LaborElectrical labour — ev charger install29.2 hr$118.11$3,448.88
Total$4,932.60

Activity

Notes on this job

  • JA
    Junia AldermanFeb 13

    Permit submitted. Waiting on the county.

Customer

Open
Marsh Landing Townhomes
Desmond Whitaker
Property Manager
6518 Copperfield Row
Seminole, FL 33838

Timeline

  1. Lead created
    Jan 19, 2025
  2. Bid lost
    Feb 4, 2025

Lost: Project cancelled by owner