Command Palette
Search for a command to run...
Board
Open
JOB-1960Paid
Panel Upgrade — 400A Service, Copperfield Condominium Association
Copperfield Condominium Association · Building B — Loading Dock
$5,628
Panel Upgrade
Scope of work
Remove obsolete panel and install new load center. Work to be performed outside business hours. All work per NEC and local amendments.
Line items
Materials, labor, and fees
| Description | Qty | Unit | Amount |
|---|---|---|---|
| Material100A Main Breaker Load Center, 24-space | 2 ea | $308.66 | $617.32 |
| Material12 AWG THHN Copper, White — 500 ft spool | 3 spool | $200.81 | $602.43 |
| Material8 AWG THHN Copper — 500 ft spool | 1 spool | $484.38 | $484.38 |
| PermitPermit and inspection fees | 1 ea | $209.67 | $209.67 |
| LaborElectrical labour — panel upgrade | 31.5 hr | $117.92 | $3,714.49 |
| Total | $5,628.29 | ||
Customer
Copperfield Condominium Association
Rosalind Thackeray
Property Manager
7164 Lakemont Loop
Temple Terrace, FL 33702
Temple Terrace, FL 33702
Assigned crew
Crew 4 — Power & Standby
Timeline
- Lead createdJul 11, 2023
- WonJul 28, 2023
- ScheduledAug 16, 2023
- CompletedAug 18, 2023