Generator Install + 200A ATS — Silverbrook Apartments

Silverbrook Apartments · Parking Structure

$20,989
Generator Install

Scope of work

Set generator pad, run gas and electrical, commission unit. Includes as-built markup on completion. All work per NEC and local amendments.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material12 AWG THHN Copper, White — 500 ft spool1 spool$200.81$200.81
Material200A Main Breaker Load Center, 40-space1 ea$609.04$609.04
Material20A Single-Pole Breaker5 ea$16.25$81.25
Material10 AWG THHN Copper, Red — 500 ft spool3 spool$305.45$916.35
Material400A Meter Main Combo, 42-space1 ea$1,721.36$1,721.36
PermitPermit and inspection fees1 ea$282.93$282.93
LaborElectrical labour — generator install145.6 hr$117.97$17,177.04
Total$20,988.78

Job photos

4 from the field · click to enlarge

Activity

Notes on this job

  • EV
    Emmett VanceJun 16

    Materials staged at the shop, ready for Monday.

Customer

Open
Silverbrook Apartments
Anika Alderman
Regional Manager
5666 Sawgrass Reach Dr
Plant City, FL 33630
Assigned crew
Crew 4 — Power & Standby

Timeline

  1. Lead created
    May 17, 2025
  2. Won
    Jun 20, 2025
  3. Scheduled
    Jul 7, 2025
  4. Completed
    Jul 15, 2025