3

Command Palette

Search for a command to run...

Board
JOB-2064Lost

EV Charging Expansion Phase 2 — Heron Cove Villas

Heron Cove Villas · Building B — Front Office

$6,307
EV Charger Install

Scope of work

Install Level 2 EV charging equipment with dedicated circuit. Work to be performed outside business hours. Permit and inspection included.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material400A Meter Main Combo, 42-space1 ea$1,721.36$1,721.36
Material20A Double-Pole Breaker2 ea$36.97$73.94
Material4/0 AWG Aluminum SER Cable55 ft$8.22$452.10
LaborElectrical labour — ev charger install34.4 hr$118.01$4,059.48
Total$6,306.88

Activity

Notes on this job

  • EV
    Emmett VanceJul 24

    Walked the site with the customer. Scope confirmed, no surprises.

Customer

Open
Heron Cove Villas
Arturo Mercer
Property Manager
4430 Osprey Landing Blvd
Largo, FL 33864

Timeline

  1. Lead created
    Jul 18, 2024
  2. Bid lost
    Aug 1, 2024

Lost: Went with incumbent contractor

Documents