3

Command Palette

Search for a command to run...

Board
JOB-2110Lead

EV Charging Expansion Phase 2 — Harborlight Townhomes

Harborlight Townhomes · Building F — Community Center

$9,625
EV Charger Install

Scope of work

Add EV charging capacity including panel work and conduit run. Customer to provide site access during working hours.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material50A Double-Pole Breaker11 ea$58.90$647.90
Material20A Single-Pole Breaker5 ea$16.25$81.25
LaborElectrical labour — ev charger install75.4 hr$117.98$8,895.49
Total$9,624.64

Customer

Open
Harborlight Townhomes
Marcus Winthrop
Property Manager
4530 Marsh Landing Pkwy
Clearwater, FL 34129

Timeline

  1. Lead created
    Jul 30, 2026