Add EV charging capacity including panel work and conduit run. Final walkthrough with customer before sign-off. Includes as-built markup on completion.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
MaterialLevel 2 EV Charger, 48A Hardwired4 ea$862.22$3,448.88
Material20A Double-Pole Breaker5 ea$36.97$184.85
LaborElectrical labour — ev charger install52 hr$117.99$6,135.48
Total$9,769.21

Job photos

2 from the field · click to enlarge

Customer

Open
Heron Cove Villas
Arturo Mercer
Property Manager
9521 Pinecrest Commons
Seminole, FL 34295
Assigned crew
Crew 4 — Power & Standby

Timeline

  1. Lead created
    Oct 22, 2024
  2. Won
    Nov 7, 2024
  3. Scheduled
    Nov 12, 2024
  4. Completed
    Nov 13, 2024