Service Upgrade — 200A Meter Main, Bayshore Condominium Association

Bayshore Condominium Association · Building C — Front Office

$3,798
Panel Upgrade

Scope of work

Remove obsolete panel and install new load center. Permit and inspection included. All work per NEC and local amendments.

Line items

Materials, labor, and fees

DescriptionQtyUnitAmount
Material10 AWG THHN Copper, Red — 500 ft spool3 spool$305.45$916.35
Material20A AFCI/GFCI Dual-Function Breaker3 ea$77.40$232.20
PermitPermit and inspection fees1 ea$256.32$256.32
LaborElectrical labour — panel upgrade20.3 hr$117.86$2,392.65
Total$3,797.52

Customer

Open
Bayshore Condominium Association
Anika Castellanos
Board President
7289 Whitecap Ter
Dunedin, FL 33720
Assigned crew
Crew 4 — Power & Standby

Timeline

  1. Lead created
    May 19, 2025
  2. Won
    Jun 5, 2025
  3. Scheduled
    Jun 20, 2025
  4. Completed
    Jun 29, 2025

Documents